|
?Budgets are tight for many smaller universities. We
needed to replace two older chillers and we needed to make the right decision
fast.?
This was
the situation facing Capital University in Columbus, Ohio in late 1998,
according to Frederick McKinney, the superintendent of buildings and grounds.
Located in the suburb of Bexley, Capital is a private liberal arts college with
a total enrollment of about 4,000. It features well-maintained brick buildings
with ivy-covered walls and shaded grassy walks. The buildings on campus are
heated by a central plant and most are also cooled by a central chilled water
plant.
The
need to replace chillers had been developing for several years. The school had
previously relied on a central chilled water plant with two single-stage steam
absorption chillers, one a 650-ton and the other a 750-ton. The two machines
were 33 years old and approaching the end of their useful life. The school had
started to evaluate replacement options and retained ThermalTech Engineering of
Cincinnati, Ohio to evaluate options.
McKinney
said the university had worked with ThermalTech on mechanical engineering and
energy management projects for many years. The situation suddenly became more
critical when the absorption chillers failed ? with little hope of repair ?
right in the middle of the 1998 cooling season. The school temporarily rented
chiller capacity to get through the cooling season and asked ThermalTech to
accelerate it research on chiller plant options. The goal was to have
replacement capacity online in time for the 1999 cooling season.
There
were about 20 potential scenarios for equipment replacement, initially. These
were narrowed down to a smaller number of practical choices based on life-cycle
economics. The engineer reviewed options that would be reliable, economical and
could be installed by the beginning of the next cooling season.
McKinney
adds that the university and consultant wanted a system that would be viable
well into the future. ?We needed a system that would meet our needs for the
next 20-25 years.? He said that the school also was planning to build a new
sports complex and this would increase the amount of chilled water required in
the near future. ?That was a driving force in our being sure that the new
system had extra capacity.?
Based
on the life-cycle analysis and its familiarity with the university?s
situation, the consultant recommended installing electric centrifugal chiller
capacity. However, ThermalTech also recognized that, with the absorption
chillers being removed from service, the school risked higher natural gas costs
because of the potential loss of an advantageous gas rate. This rate required
the use of 30% of its total gas usage during the summer months. With this in
mind, ThermalTech suggested consideration be given to an engine-driven
centrifugal chiller fired on natural gas to meet at least part of the cooling
load.
GAS-POWERED OPTION ATTRACTIVE
The school decided to purchase a system with two
1,000-ton centrifugal chillers and an 800-hp natural gas engine-generator set
that could supply either of the chillers at full load. The system selected was a
Trane gas-powered CenTraVac (GPC) chiller package consisting of two Trane Model
CVHF 1,000-tone two-stage centrifugal chillers with an accompanying Waukesha
Enginator rated at 560 kW at 1,800 rpm.
The
Waukesha engine is a liquid-cooled V-12 design and the Kato generator delivers
electric power at 460V. ThermalTech designed the system to allow the engine to
supply energy to either of the chillers through a dual transfer switch. The
switch also provided positive assurance that the chiller being supplied through
the engine-generators was disconnected from the utility power supply. University
personnel expressed concern with the engine initially. Their comfort was
established through visits to similar operating sites, and by touring Trane and
Waukesha factories with Trane representatives.
The
new chiller plant design incorporated a low-flow condenser water flow feature (2
gpm/ton) to minimize tower requirements and pumping energy. The design also
features variable primary pumping to reduce pumping energy. Each campus building
was retrofitted with an energy delivery station to optimize chilled water flows.
The Trane chiller plant control system uses a BACnet interface with the
university?s existing facility management system.
With
the removal of the old absorption machines, there was ample space for the new
chillers. Unlike other systems that mechanically connect the engine and chiller,
with the CenTraVac-Enginator combination the engine-generator unit can be
located remotely from the chiller. In this case the engine was located in an
adjacent room, which was remodeled to allow it to be acoustically isolated from
the rest of the chiller plant. Another advantage of the remote location is that
the generator can power either chiller if one is down for maintenance. Further,
it can be used to provide backup electric power generation for other buildings
in the event of a power failure.
ACOUSTICS,
DEADLINE CONCERNS
Acoustics was an important consideration in the
project. The chiller plant is only about 150 feet from the university?s
Conservatory of Music Building. ?We were concerned about acoustics,?
McKinney said. ?That?s one reason we chose to use a hospital-grade muffler
on the engine. Since we?ve started up there have been zero complaints about
acoustics.?
Another
one of McKinney?s concerns had been getting all the equipment delivered and
installed in time for the necessary spring startup. The university did not
approve proceeding with the replacement until November of 1998. ThermalTech
worked with Trane to pre-purchase all of the major components and expedite
deliveries. By careful planning and use of expedited equipment deliveries, the
engineer and manufacturers were able to achieve a fast-track schedule and assure
that both proper design and commissioning could be performed.
As
it turned out, the plant was started up on schedule April 1, 1999, and has been
operating smoothly since then. The two chillers alternated running on the engine
through most of the summer of 1999. At present load levels, the campus can be
carried on a single chiller on even the hottest days. With the projected
completion of the new Athletic Complex in 2001 and extension of chilled water
service into the few campus buildings not currently cooled by the central plant,
it will be necessary to use both chillers on the hottest days. Even with these
additions, McKinney is confident that the university has adequate capacity for
the foreseeable future.
Energy
and control specialist Rex Fisk is responsible for running the plant. He notes
that an additional advantage of the new system is that ?It can bring the
chilled water system down to its operating temperature of 44 degrees Fahrenheit
within 20 minutes.? This compares to a matter of hours for the previous
system. This is a particularly valuable feature during the spring or fall months
when there is a sudden need for chilled water on a warm day, Fisk said.
The
mechanical room containing the chillers features a window that looks into the
engine room. This allows visual observation of the engine and its gauges without
the need to enter this separate room. Two cooling towers on the roof of the
plant building serve to cool both condenser cooling water and engine jacket
water.
ENGINE OPERATION
The engine-generator for the chiller is operated
during most of the summer months. This has been the advantage of using the
necessary proportion of natural gas fuel that allows the university to take
advantage of the low gas rate. This use pattern also assures that summer
electric peak demand is minimized.
In
addition, McKinney notes that the ability to run a chiller on either natural gas
or electricity places the owner in a stronger and more flexible position in the
future. ?On any given day, we can decide which energy source to use. We?re
less at the mercy of changing future energy supplies or prices.? McKinney said
it is unknown what effect future utility deregulation will have. ?But whatever
happens, we?re in a better position with a choice of energy sources.?
|