|
The implementation of a Reliability Centered Maintenance
or RCM program begins with a solid and practical Preventive
Maintenance (PM) program. Implementing a PM program requires
a critical and in-depth review of the operations and equipment
within the business. An overview of an actual implementation
follows.
A manufacturing business with 2,400 employees in four
plants had over 3,000 pieces of production equipment ranging
from instrumentation and state-of-the-art, sophisticated
machining centers to 100 year old forge presses. Virtually
all maintenance was done in a reactive mode: If something
broke, Maintenance was informed and a craftsman was assigned
to facilitate the necessary repairs. The company implemented
very successful PM, PdM, and RCM programs coupled with a
continuous improvement program and a computerized maintenance
management system (CMMS), over a period of less than four
years.
One of the first programs identified, as a necessary foundation
from which to build, was a solid and practical PM program.
The initial program took nine months to develop and began
with the assignment of individuals to a PM task team. Individuals
were chosen from maintenance supervision, maintenance planning,
and the trades for the nine-person team.
Initially, the team looked at segregating the business
operations into four major groupings:
1) Government-owned equipment
2) Safety-related equipment
3) Facilities equipment
4) Manufacturing equipment
This company was a government contractor, and, as such,
utilized some Government-owned equipment in its manufacturing
process. The requirements of maintaining this type of equipment
are quite specific. Hence, PM’s were critical on this
equipment due to contractual issues.
Once the four major groupings were defined, they were
prioritized with the most critical grouping being Government-owned
followed by safety-related, facilities, and manufacturing.
With over 3,000 separate pieces of equipment to maintain,
the implementation of a comprehensive PM program appeared
daunting at first. The plan, however, was to break down
the implementation into manageable bites. The team decided,
once the four major groupings were identified, that only
the critical equipment in each grouping would be put on
the PM program initially. The total number of pieces of
equipment initially were limited to 250 pieces.
The finalized PM work order instructions for each of the
250 pieces in the core PM program were completed, and the
maintenance planners developed a schedule for which PMs
would be done and when during the calendar year. The maintenance
planners leveled the PM work orders throughout the year
to allow for a relative level loading of man-hours on a
weekly basis.
In the following two and a half years, all of the equipment
in the plants was added to the PM program with a total of
over 3,000 within a little over three years from the inception
of the PM program. The format used for PM work instruction
development was followed on subsequent equipment additions
to the program. New equipment to the plant operations utilized
the manufacturer’s recommendations until such time
as sufficient experience was gained by Maintenance to adjust
the PM work instructions and frequencies. The intent was
not to have a static PM program, but insure it was dynamic
to meet the changing business needs coupled with the experience
gained in maintaining the equipment.
As the traditional PM program was developed, additional
predictive maintenance (PdM) methodologies were implemented
for appropriate equipment such as lubrication analysis,
thermography, vibration analysis, etc. The PM program coupled
with PdM and the data accumulated with a CMMS allowed maintenance
to enter RCM. Reliability Centered Maintenance addresses
the root cause of problems rather than just production reliability.
Typically, organizations do not see the benefits of RCM
initially, and, rather, see it as an additional and unnecessary
expense to the business since benefits are not immediately
noticeable.
For instance, some equipment may be taken out of service
more frequently or for longer periods than prior to RCM.
This translates into reduced availability to operations
in the initial phase. However, the intent in doing so is
to identify and address the root causes of failures thereby
improving the cost effectiveness of equipment to the business.
In other words, the equipment will operate more reliably
long term over the traditional PM program.
LUBRICATION PROGRAM: This business realized it did not
have the resources in-house to implement and maintain an
effective lubrication program in the areas of program development,
people to do the work, and equipment to analyze and monitor.
The decision was made to contract with an outside source
to implement and manage the entire program.
The lubrication program followed a similar implementation
strategy as the PM program. Only certain critical equipment
was selected to be included in the initial start-up of the
program. Equipment was selected in part due to its criticality
to the business, redundancy of equipment (such as three
of dozens of similar machining centers), historical problems
which appeared to be lubrication-oriented, and of such a
nature to test the resources of the lubrication vendor.
Once equipment was identified, the lubrication vendor
conducted a thorough analysis of each piece of equipment
to determine its current state. Recommendations were made
to the business as to the correct lubricants and coolants
to use for each application. The lubrication vendor assumed
full responsibility for the lubrication requirements including
sample collection, analysis, reporting, monitoring, recommendations
to the business for maintenance on the equipment relative
to lubrication, training of the business’s employees
in the proper methods to lubricate equipment, etc.
THERMOGRAPHY: A thermography program was developed, concentrating
on the electrical substations and switchgear initially for
the four plants. The program was developed by the plant
electrical engineer. Actual thermographic monitoring was
contracted out to a vendor with the expertise and equipment
necessary to do effective thermography.
The results of the thermographic studies, conducted as
part of the PM program, were translated into planned maintenance
work orders for completion as scheduled by the maintenance
planners. Much of the work on substations and switchgear
was scheduled for annual plant shutdown outages unless it
was indicated that the problems had to be addressed sooner.
VIBRATION ANALYSIS: Vibration was measured on selected
equipment due to its criticality to the business and high
rotating speeds. Air compressors were the primary equipment
monitored by the plants.
The data collected from these programs along with data
from other sources, such as the Instrumentation and Calibration
Program, were feed into the CMMS as the central repository.
Access to the data was not limited to any individuals or
job positions. However, only selected people were authorized
to make entries or change any data to insure system integrity.
Process Improvement Teams were formed within maintenance
with representatives from the trades and staff of maintenance.
The teams were trained in Continuous Improvement and process
improvement techniques including:
• Data Collection
• Data Evaluation
• Problem Solving
• Statistical Process Control
• Control Charts
• Pareto Charts
• Histograms
• Failure Rate Run Charts
• Failure Rate vs. Maintenance Costs
• Weibul Analysis
• Mean Time Between Failures
• Root Cause Failure Analysis
Utilizing the results obtained allowed the PM and PdM
programs to be tailored specifically to the operating conditions
of the equipment. In addition, problem solving identified
the root causes for the most common and most expensive failures
of equipment. Operating expense savings were realized with
RCM along with an increase in manufacturing equipment uptime.
In addition to comprehensive PM, PdM, and RCM programs
and process improvement teams, the involvement of people
from all levels within Maintenance dramatically increased
the collection and utilization of good data within the CMMS.
Additionally, the craftsmen and salaried people within Maintenance
increased their knowledge and use of the CMMS. An additional
off-shoot was the interest in the data collected in the
CMMS by people in organizations outside of maintenance,
such as Finance, Purchasing, Manufacturing, Engineering,
Environmental-Health-Safety, etc. who saw an additional
resource available to them to assist them in their daily
jobs.
A preventive maintenance program, properly designed, implemented,
and utilized, is critical for any Maintenance organization
trying to move into the world class category. It is, also,
a critical success factor for Reliability Centered Maintenance.
Success for this business was dependent upon the proper
identification and utilization of outside resources, training,
and team facilitation throughout the processes in this case
study.
© February, 1995
R. L. Steibly, CPE & Certified Senior Consultant
Steibly & Associates
Asset Care Management Consultants
Office: 802-747-7220
Email: steibly@earthlink.net
|