|
In a taped
interview with Dr. John H. Smith of the Metallurgy Division, National
Institute of Standards and Technology, Gaithersburg, Maryland,
Dr. Smith discusses how failure analysis in the field often impacts
Engineering Standards. Using slides Dr. Smith discusses and illustrates
two specific cases where this has happened. The first of these
cases involved the failure of an oil storage tank that was relocated
from Cleveland to Pittsburgh. The other case involved the failure
of a compressed natural gas trailer tube in Litchfield, Kentucky.
In each of these cases, compliance with existing construction
and/or building codes failed to prevent failures that ultimately
resulted in serious consequences.
Objective:
The objective of studying and analyzing cases like this is threefold.
First there is the objective of preventing future failures. The
second objective is to identify corrective action(s), and the
third is to advance engineering practice. Some would even add
a fourth objective of "to find fault."
Background:
The background for the oil storage tank failure is as follows:
the tank involved was a four million gallon circular tank that
was built in 1940 for Ashland Oil Company in Cleveland, Ohio.
Beginning in 1940, the tank was operated for many years in what
was believed to have been heated oil service. It is unclear as
to how many years the tank was not used, but in 1986 it was disassembled
by cutting it apart into sections. Using oxy-acetylene torches
the "old welds" were left in place as the tank was cut
apart and the sections were moved to an Ashland Oil facility near
Pittsburgh, Pennsylvania. Using shielded metal arc welding, the
tank was reassembled in 1987 and placed in a tank farm with many
other similar tanks near the Monongahela River. When reassembled,
the tank joints were x-rayed and leak tested. Test results indicated
that none of the welds required rework. The reassembled tank was
50 feet high and approximately 120 feet in diameter. A dike was
built around the tank that would hold 150 percent of the tank
capacity.
The tank was
partially filled with diesel fuel in August 1987. On January 2,
1988, during its initial filling to capacity after reconstruction,
the tank failed catastrophically creating a tidal wave of oil
that sent nearly 500,000 gallons of diesel fuel into the Monongahela
River causing a major environmental problem. The problem was so
severe that the entire water supply for all of South Pittsburgh
had to be shutdown for two weeks. In addition to spilling thousands
of gallons of oil in the river, the tidal wave of oil from the
tank damaged other nearby tanks and structures as well. "A
small, uncemented cinderblock shed about 120 feet distant had
its walls literally swept away
leaving its roof lying neatly
on the slab floor. "
Eyewitness
accounts of the failure indicated that there were no warnings.
At the time of failure the tank was nearly full. There was no
explosion. An operator was on the roof of the tank to verify that
it was nearly full just five minutes before the tank ruptured.
Sounds like thunder were described as emanating from the tank
for about 30 seconds at the time of the failure. Observations
of the failure site revealed that the tank had moved about 120
feet. The roof of the tank was still attached to portions of the
tank wall. The bottom of the failed tank remained intact. Collateral
damage included a fifty feet high adjoining tank that had oil
on its roof and another tank some distance away that had oil all
over it and was physically damaged.
Description
of the experiment or process: In a failure of this type, several
failure hypotheses immediately come to mind and are investigated.
The investigative team involved in this failure consisted of Dr.
Smith and other experts. They concluded that the failure possibilities
were some external event, an operational failure, a foundation
failure, a structural failure, and/or a material failure. To test
for these type failures, many tests were called for and performed.
They included stress analysis, finite element analysis, and thermal
analysis to determine both the metal temperature and oil temperature
at the time of failure. Also, Foundation Evaluation studies were
performed to see if some form of settling had created stresses
in the vessel walls. Materials Characterization analyses were
performed to identify the materials and properties of the tank
metal and welds. Structural analysis and fracture analysis was
performed to evaluate the base metal and the weld metal. Finally,
hardness, strength, Charpy v-notch tests to determine brittleness,
nil ductility, fracture toughness, and tensile strength tests
were performed to determine the physical characteristics of the
tanks metallurgical microstructure.
Data to
be expected: It was expected that the results of the tests
and analysis outlined above would reveal the cause of failure
as well as its origin. This proved to be true as the failure was
found to begin with a brittle fracture in the base metal alongside
old welds with the origin of failure being an undetected flaw
in the base metal that was present prior to tank's original construction
in 1940. Repeated heating and cooling of the weld process exacerbated
this flaw. Ambient conditions (below the ductile to brittle transition
temperature of the tank metal) as well as the pressure from the
filled tank caused this flaw to yield catastrophically.
Potential analysis of the expected data: Analysis of the
expected data produced the desired result. It led to the discovery
of the root cause(s) of the failure and highlighted deficiencies
or shortcomings in engineering standards. It is unfortunate that
failures of this magnitude and the inconveniences it produced
had to happen; but, at present, this is often the only way that
deficiencies in standards can be detected.
Discussion: "Just past five o'clock p.m. on January
2, 1988, a large aboveground fuel storage tank located in Floreffe,
Allegheny County, Pennsylvania suddenly and without warning collapsed
as its shell rent completely from base to roof. The tank collapse
unleashed a tsunami of petroleum product as almost 3.9 million
gallons of diesel fuel surged out of the failed structure. The
crest of this wave washed over nearby earthen dikes, whose intended
design for containing a gradual release of petroleum products
left them pitifully inadequate to confront the force of this catastrophe."
The above
paragraph describes eloquently and with emotion how the local
press viewed this incident. The original article describes with
even more emotion how much diesel fuel flowed into the river and
how much damage was done to the ecosystem, to the tank, the structural
steel that supported it, and to other nearby structures. The same
article, taken off the Internet, while commending them for their
attitude and cooperation after the incident, is very critical
of Ashland Oil, its management and employees, and its contractors
for allowing this disaster to occur.
It is amid
all of this emotion and fault finding that the failure analyst
must operate, divorcing himself from the emotion and chaos and
focusing on the facts to determine the true cause of the failure.
In this case, as in most cases, the true cause of the failure
lay in all the wreckage and debris of the failed oil tank.
To the author(s)
of the above-mentioned report, Ashland Oil Company was at fault
for not following existing industry and government standards for
the construction and operation the failed tank. But as Dr. Smith
pointed out in his talk, there are two sets of standards. The
ones applicable to "oil storage" are those of the American
Petroleum Institute (API). The two that apply in this situation
are API 650 and 653. API 650 covers new construction only for
"Welded Steel Tanks for Oil Storage." API 653 covers
the reconstruction, repairs, and modification of existing tanks.
It was generally felt that this particular tank was covered under
API 653. Of course, as was also pointed out by Dr. Smith, compliance
with the standards is voluntary except in certain cases where
they are mandatory by law. For example, the Clean Water Act requires
compliance with standards in certain cases.
API Standard
650 for new construction requires that 15 foot-pound Charpy energy
at +5ºF "semikilled" steel be used, and a that
full hydrostatic test be performed. If reconstruction of the failed
tank had followed this standard, in all likelihood the failure
would have been averted. However, it was rebuilt to the less stringent
API 653. After the failure and subsequent investigation the failure
did serve as a vehicle for bringing about changes in the API 653
standards.
The new API
Recommended Practice 653, (1990) "Tank Inspection and Repair"
which covers maintenance, inspection, repair, alteration, and
relocation of storage tanks now provides a procedure to assess
risk of brittle fracture. It is based on API standard 650 and
the "Assessment" is based on a decision tree to determine
the risk of brittle fracture. When this practice is followed,
failures like the one discussed in this paper will no longer happen
and engineering practice will have been advanced.
As discussed
by Dr. Smith, any failure in service is an engineering design
failure, and we should learn from it. When we learn from the failure,
engineering practice is advanced and if necessary the appropriate
Engineering Codes and Standards like SAE, API, AGA, ASTM, and
ASME are changed to reflect the lessons learned. The lessons learned
from the Liberty Ship failures of World War II created a whole
new discipline of engineering - Fracture Mechanics. Fracture Mechanics
has been in practice for more than 50 years and has advanced our
knowledge of materials failures and how to prevent them tremendously.
Finally, since
there are literally thousands of tanks just like or similar to
the one that failed in Pittsburgh scattered all across the United
States along the rivers near major cities, the API conducted a
survey of existing tank owners. The API wanted to compile a list
of failure data and material toughness data to review their toughness
standards. They found that they were able to gather data on 54
failed tanks of welded and riveted construction. The tanks were
built between 1897 and 1979 and had a capacity ranging from 55,000
to 186,000 barrels. The age at failure ranged from 0 to 51 years,
and the temperature at which they failed ranged from 0ºF
to 51ºF. Most of the tanks failed after a repair or modification.
This data was used to develop the decision tree for tank assessment
that was incorporated in the API standards. Both API standards
650 and 653 were modified based on the oil tank failure investigation
and the survey data.
The other
failure discussed by Dr. Smith was the failure of a Compressed
Natural Gas Trailer Tube. This failure occurred in October 1997
in Litchfield, Kentucky during the filling of the tube from a
natural gas well. The tube was a DOT Type 3T (2725-psi) 22-inch
diameter, approximately 40-feet long seamless steel tube for CNG
service. It was made from A-372, Class 5, quenched and tempered
steel with a tensile strength of 160-170 ksi. It had been in use
for approximately one week. The failure involved the complete
rupture of the tube.
The failure
investigation showed that the tube had failed from environmentally
assisted cracking due to about 550 parts per million water and
hydrogen sulfide in the gas. The fix for this problem actually
required the use of a lesser quality steel. The Department of
Transportation (Dot) issued Exemption E-8009 for tube steel used
in Compressed Natural Gas service. The exemption specified the
following:
· Limit CNG to 3AAX tubes
· Maximum tensile strength 126 ksi
· Tubes be marked "CNG"
· 1800 -2800 psi pressure
· Gas purity requirements of 0.5 lb./million water, and
0.1 gr./100 cu. ft. hydrogen sulfide
Present
System for Changing Engineering Practices. The present system
for changing engineering practices is done on an "Ad Hoc"
basis. This is very inefficient and should be changed. For example,
maybe Engineering Data Centers could be established at the various
code and standards organizations like API, SAE, ASTM, ASME, etc.
to act as a clearinghouse for suggested code changes based on
valid failure analyses findings from professional engineers across
the country. The need exists for something like this because of
our decreased tolerance for failures and the potential environmental
impact and increased liability of certain failures. Also, there
is an increased public perception about the significance of failures
and the concern for worker safety throughout the country. Fortunately,
no one was killed or seriously injured in the oil tank failure
discussed in this paper, but the potential for those type consequences
was certainly there.
References:
References for this paper are:
- A taped
interview on "The Impact of Failure Analysis on Engineering
Practice" with Dr. John H. Smith, Metallurgy Division,
National Institute of Standards and Technology, Gaithersburg,
Maryland.
- Failure
Mechanisms and Effects Laboratory, ENRE674, Module 3, The
Impact of Failure Analysis on Engineering Practice, pages
3-1 through 3-7
- Storage
Tank Collapse Sends 500,000 Gallons Of Diesel Fuel into Monongahela
River, Pennsylvania's Environmental Heritage, June
1988
William C.
Worsham is a Senior Consultant and Trainer for Reliability Center,
Inc. Mr. Worsham has over 30 years experience in the field of
Maintenance and Reliability program management. He has participated
in and led teams in the development, design and implementation
of three separate maintenance management systems. He has also
participated in the design and implementation of specialized reliability
inspection programs such as lubrication scheduling, vibration
monitoring, instrument inspection and preventive maintenance.
Mr. Worsham is a practitioner of root cause analysis in the field
with his clientele as well as an educator. He can be contacted
at 804/458-0645 or bworsham@reliability.com.
|