Craft Labor-A Terrible Thing to Waste:
Improving Overall Craft Effectiveness is very key question
we need to answer. Getting maximum value from craft labor
resources and higher craft productivity requires measurement
and knowing where you are now.
Maintenance operations that continue to operate in a reactive,
run-to-failure, fire fighting mode and disregard implementation
of today’s best practices will continue to waste their
most valuable asset and very costly resource - craft time.
Typically, due to no fault of the craft work force, surveys
and baseline measurements consistently show that only about
30 to 40 percent of an eight-hour day is devoted to actual,
hands-on wrench time.
It is very important to understand; “How your valuable
craft time can slip away” as illustrated in Figure
2. Best practices such as effective maintenance planning/scheduling,
preventive/predictive maintenance, more effective storerooms
and parts support all contribute to proactive, planned maintenance
and more productive hands on, “wrench time”.
Measuring and improving overall craft effectiveness (OCE)
must be one of many components to continuous reliability
improvement process and total asset management. As we discussed
in Part I, OCE includes three key elements very closely
related to the three elements of the OEE Factor.
Overall
Craft Effectiveness(OCE) |
Overall
Equipment Effectiveness(OEE) |
Elements
of OEE and OCE |
| 1.
Craft Utilization or Pure Wrench Time (CU) |
Asset Availability/Utilization (A) |
Effectiveness |
| 2.
Craft Performance (CP) |
Asset
Performance (P) |
Efficiency |
| 3.
Craft Service Quality (CSQ) |
Quality
of Asset’s Output (Q) |
Quality |
Craft Utilization
Craft Utilization (CU): The first element
of the OCE Factor is Craft Utilization or pure wrench time.
This element of OCE relates to measuring how effective we
are in planning and scheduling craft resources so that these
assets are doing value-added, productive work (wrench time).
Effective planning/scheduling within a proactive maintenance
process is key to increased wrench time and craft utilization.
It’s having an effective storeroom with the right
part, at the right place in time to do scheduled work with
minimal non-productive time on the part of the crafts person
or crew assigned to the job.
Pure wrench time is just that and does not include time
caused by the following:
-
Running/traveling from emergency to emergency in a
reactive, fire fighting mode
-
Waiting on parts and finding parts or part information
-
Waiting on other asset info, drawings, repair instructions,
documentation etc.
-
Waiting for the equipment to be shut down
-
Waiting on rental equipment or contractor support to
arrive at job site
-
Waiting on other crafts to finish their part of the
job
-
Traveling to/from job site
-
Make-ready, put away or shop clean up time
-
Meetings, normal breaks, training time and excessive
troubleshooting due to lack of technical skills
-
Lack of effective planning and scheduling
Craft Utilization (or wrench time) can be measured and
expressed simply as the ratio of:
Total Productive (Wrench Time)
CU% = Total Craft Hours Available & Paid x 100
Improve Wrench Time First: Go on the attack
to increase wrench time in your operation even if you do
nothing to improve the other two OCE Factors; Craft Performance
and the Craft Methods and Quality level. As we will see
in the following examples, very dramatic and significant
tangible benefits can be realized with just focusing on
increasing wrench time. Improvement of from 20 to 30 percentage
points can typically be expected just from more effective
maintenance planning and scheduling. Let’s now look
at several examples showing the value of craft utilization
improvement within a 20-person work force with an average
hourly rate of $18.00 and see the significant benefits that
a 10 percent increase in craft utilization can provide.
Gained Value of 10% in Wrench Time: What
if through better planning and scheduling, good parts availability
and having equipment available to fix it on a scheduled
basis, we are able to increase actual wrench time by 10
percent? What is the gained value to us if we get wrench
time increase across the board for a 20- person crew being
paid an average hourly rate of $18 per hour? First let’s
look at what it is really costing us at various levels of
wrench time
Total Craft Hours Available and Annual Craft Labor Costs
for Crew of 20 Crafts
Hrs.
20 Crafts x 40 wk. x 52 wks./yr. = 41,600 Craft Hours Available
41,600 Craft Hours @ $18/hr. = $748,800 Craft Labor Cost/Year
Wrench Time and Actual Costs Per Hour at Various Levels
of Craft Utilization
Level
of
Craft Utilization |
Total
Wrench Time (Hours) |
Actual
Hands On
Cost Per Hour |
Average
Wrench Time Hours Per Craft Position |
30% |
12,480
|
$60.00 |
624 |
40% |
16,640 |
$45.00 |
832 |
50% |
20,800 |
$36.00 |
1040 |
60% |
24,960 |
$30.00 |
1248 |
70% |
29,120 |
$25.71 |
1456 |
80% |
49,920 |
$22.50 |
1664 |
*85% |
35,360 |
$21.18 |
1768 |
90% |
37,440 |
$20.00 |
1872 |
100% |
41,600 |
$18.00 |
2080 |
Note: Maximum possible Craft Utilization is 85 percent (as
shown in Figure 2) considering paid holidays, vacation time,
breaks, clean-up, employees meetings, craft training, etc.
Example: What If Wrench Time is 40%? With
effective planning and scheduling we can achieve at a minimum
a 10 point improvement in craft utilization from our current
baseline. Starting from a baseline of 40 percent up to a
level of 50 percent, we in effect get a 25 percent increase
in craft capacity for actual work.
• Total Hours Gained in Wrench Time: 4,160 hours
gained
20,800 hours @ 50% - 16,640 hours @40% = 4,160 hours gained
• Total Gain in Equivalent Number of Crafts Positions:
5
4,160 Hours Gained
832 Average Wrench Time Hours @ 40% = 5 Equivalent Craft
Positions
• Total Gained Value of 5 Equivalent Positions: $187,200
hrs. Wks $18.00
5 equivalents x 40 wk. x 52 yr. x hr. = $187,200 Gained
Value
Valuable Craft Time Can Slip Away: For the 20 person craft
work force, just a 10% improvement up to 50% wrench time
is 4,160 hours of added wrench time. This gain represents
a 25 percent increase in overall craft labor capacity. The
maintenance best practice for planning and scheduling requires
a dedicated planner(s). An effective maintenance planner
can support and plan for 20 to 30 crafts positions. With
only a 10 percent increase in craft utilization for a 20-person
craft work force, we can get more than a 5 to 1 return to
offset a maintenance planner position.
Example B: What if Wrench Time is 30%?
For many operations wrench time is only about 30%. Again
with effective planning and scheduling, good PM/PdM and
parts availability we can eliminate excessive non-wrench
time. An improvement of at least 20 points in craft utilization
is very realistic. If we begin from a baseline of 30% up
to a level of 50% we are in effect getting a 67% percent
increase in craft capacity for actual hands on work.
Let’s look at the gained value we can get from going
from 30% up to 50% wrench time.
• Total Hours Gained in Wrench Time: 8,320 Hours
Gained
20,800 hours @ 50% - 12,480 hours @30% = 8,320 hours gained
• Total Gain in Equivalent Number of Crafts Positions:
13
8,320 Hours Gained
624 Average Wrench Time Hours @ 30% = 13.3 Equivalent Craft
Positions
• Total Gained Value of 13.3 Equivalent Positions:
$497,952
hrs. Wks $18.00
13.3 equivalents x 40 wk. x 52 yr. x hr. = $497,952 Gained
Value
Valuable Craft Time Can Be Regained: Tremendous
opportunities are available for the 20 person craft work
force with wrench time currently in the 30% to 40% range.
Just a 10% to 20% improvement up to 50% wrench time can
be from 4,000 to 8,000 hours of added wrench time. This
gain represents a 25% to 67% increase in overall craft labor
capacity. There are a number of best practices to help you
regain valuable craft resources. The maintenance best practice
for planning and scheduling requires a dedicated planner(s).
An effective maintenance planner can support and plan for
20 to 30 crafts positions.
Use your CMMS/EAM as a mission-essential information technology
tool that supports planning and scheduling, better MRO materials
management and effective preventive maintenance, three best
practices for improving craft wrench time. Bottom line results
that give us 5 to 13 more equivalent craft positions and
up to $500,000 in gained value of more wrench time with
existing staff, can be dramatic proof that internal maintenance
operations can be profit centered.
CRAFT PERFORMANCE
Craft Performance (CP): The second key
element affecting Overall Craft Effectiveness is craft performance.
This element relates to how efficient we are in actually
doing hands-on craft work when compared to an established
planned time or performance standard. Craft performance
(CP) is expressed as the ratio of:
Total Planned Time (Hours)
CP% = Total Actual Craft Hours Required x 100
Craft performance is directly related to the level of individual
craft skills and overall trades experience as well as the
personal motivation and effort of each craftsperson or crew.
Effective craft skills training and technical development
contribute to a high level of craft performance.
Craft Performance Calculation: The planned
time for a minor overhaul or PM procedure is 10 hours based
on a standard procedure with parts list, special tools,
permits required, etc.
• If the job is completed in 12 hours, then Craft
Performance = x 100 = 83%
• If the job is completed in 9 hours, then Craft
Performance = x 100 = 111%
An effective planning and scheduling function requires that
reasonable estimates and planning times be established for
as much maintenance work as possible. Since maintenance
work is not highly repetitive, the task of developing planning
times is more difficult. However there are a number of methods
for establishing planning times for maintenance work including:
-
Reasonable estimates: A knowledgeable person either
a supervisor or planner uses their experience to provide
their best estimate of the time required. This approach
does not scope out the job in much detail to determine
method or special equipment needed.
-
Historical data: The results of past experience are
captured via the CMMS or other means to get average
times to do a specific task. Overtime, a database of
estimated time is developed which can be updated with
a running average time computed for the tasks.
-
Predetermined standard data: Standard data tables for
a wide range of small maintenance tasks have been developed.
Standard data represents the building blocks that can
then be used to estimate larger, more complex jobs.
Each standard data table provides what the operation
is, what is included in the time value and the table
of standard data time for the variables that are included.
The Universal Maintenance Standards (UMS) method used
back in the 1970’s represents a predetermined
standard data method.
The ACE Team Benchmarking Process: As
a means to overcome many of the inherent difficulties associated
with developing maintenance performance standards, the ACE
(A Consensus of Experts) Team Benchmarking Process.
This process was developed back in 1978 by Ralph W. “Pete”
Peters, founder of The Maintenance Excellence Institute
(MEI). This method, based upon principles of the Delphi
Technique, relies primarily on the combined experience and
estimating ability of a group of skilled crafts personnel.
The objective is to determine reliable planning times for
a number of selected “benchmark” jobs.
This team based process using skilled craft people places
a high emphasis on continuous maintenance improvement to
reflect improvements in performance and methods as they
occur.
Generally, the ACE Team Benchmarking Process parallels
the UMS (Universal Maintenance Standards) approach in that
the “range of time concept” and “slotting”
is used once the work content times for a representative
number of “benchmark jobs” have been established.
The ACE Team Benchmarking Process focuses primarily on
the development of work content times for representative
“benchmark jobs” that are typical of the craft
work performed by the group (Peters 1978).
Once a number of benchmark job times have been established,
these jobs are then categorized onto spreadsheets by craft
and task area and according to work groups which represent
various ranges of times.
Spreadsheets are then set up with 4 work groups/sheet with
each work group having a time slots or “range of time”.
For example, work group E would be for benchmark jobs ranging
from 0.9 hours up to 1.5 hours and assigned a standard time
(slot time) of 1.2 hours.
Like wise, work group F would be for benchmark jobs ranging
from 1.5 hours up to 2.5 hours and assigned a standard time
of 2.0 hours. Spreadsheets include brief descriptions of
the benchmark jobs and represent pure wrench time. Work
content comparison is then done by an experience person,
typically a trained planner to establish planning times
within the 95% confidence range.
A complete users guide complete with step by step procedure,
forms and the recommended ACE Team charter for establishing
the ACE Team Benchmarking Process is available free by contacting
The Maintenance Excellence Institute at www.Pride-in-Maintenance.com
or via E-mail: info@Pride-in-Maintenance.com.
Planning Times Are Essential: Planning
times provide a number of key benefits for the planning/scheduling
process. First, they provide a means to determine existing
workloads for scheduling by craft areas and backlog of work
in each area. Planning times allow the maintenance planner
to balance repair priorities against available craft hours
and to realistically establish repair schedules that can
be accomplished as promised.
Secondly, planning times provide a target or goal for each
job that allows for measurement of Craft Performance. Due
to the variability of maintenance type work and the inherent
sensitivity toward measurement, the objective is not so
much the measurement of individual craft performance.
The real objective is measurement of the overall performance
of the craft work force as a whole. While measurement of
the individual crafts person is possible, Craft Performance
measurement is intended to be for the entire maintenance
work force that is doing skilled type work.
Craft Service Quality
Craft Service Quality (CSQ): The third
element affecting Overall Craft Effectiveness relates to
the relative quality of the repair. This element includes
quality of the actual work, where certain jobs possibly
require a call back to the initial repair thus requiring
another trip to fix it right the second time. However, Craft
Service Quality can be negatively impacted due to no fault
of the crafts person when hasty repairs, patch jobs or inferior
repair parts/materials create the need for a call back
We can measure call backs via the CMMS with special coding
of call back work orders. Typically, the CSQ element of
OCE is a more subjective value and therefore it must be
viewed accordingly in each operation. However, the Craft
Service Quality level does affect overall craft labor productivity
and the bottom line results of the entire maintenance process.
When reliable data is present for all three elements of
OCE, then the Overall Craft Effectiveness Factor can be
determined by multiplying each of these three elements:
OCE = CU% x CP% x CSQ%
Craft x Craft x Craft Service
Utilization Performance Quality
What Overall Craft Effectiveness Can You Expect? Since
OCE is a rather new concept there are actually a limited
number of case studies outside the real world experiences
of MEI staff and Alliance Members. Some organizations try
to measure just wrench time and it is accepted that 30 to
40% is typical and 70% is great.
Other organizations may measure and track craft performance
if a sound planning process and reliable planning times
are in place. Also other consulting firms shy away from
the often sensitive issue of measuring craft labor in anyway,
especially within a Union environment.
MEI feels strongly that measuring and improving productivity
of craft labor resources is essential to profit centered
maintenance and continuous reliability improvement. Measuring
and improving OCE must be addressed by today’s in
house maintenance operation. Likewise, we feel that the
Range of OCE Element Values shown in Table 4 represents
the High, Medium and Low combinations for OCE. Successful
operations can expect an OCE Factor in the High range of
65% or more.
Range of OCE Element Values
OCE Elements Low Medium High
1. Craft Utilization 30% 50% 70%
2. Craft Performance >80% 90% 95%
3. Craft Service Level >90% 95% 98%
The OCE Factor 22 % 43% 65%
Table 4: Range of OCE Element Values and OCE
All Three Elements of OCE are Important:
Maintenance craft labor may be very efficient with 100 percent
craft performance and still not be effective if craft utilization
is low and craft service quality are poor.
• Overall Craft Effectiveness = Craft Utilization
x Craft Performance x Craft Service Quality
30% x 100% x 70%
• Overall Craft Effectiveness = .3 x 1.00 x .7 = .21
x 100
• Overall Craft Effectiveness = 21% OCE
Since the nature of determining the value of Craft Service
Quality can be subjective, this element is typically not
used for calculating OCE. When this element is not used
in determining Overall Craft Effectiveness, it is still
an important part of effective planning and scheduling.
One key part of planning is determining the scope of the
repair job and the special tools or equipment that is required
for a quality repair. A continuing concern of the maintenance
planning function should be on improving existing repair
methods whether by using better tools, repair procedures,
or diagnostic equipment and using the right skills for the
job. Providing the best possible tools, special equipment,
shop areas, repair procedures and craft skills can be a
key contributor to improving Craft Service Quality.
And Craft Service Quality can often still be a key performance
indicator (KPI) that is determined from periodic review
of call backs, customer complains and customer surveys.
Therefore MEI feels that the Overall Craft Effectiveness
Factor is best determined by using just two elements for
the OCE Factor calculations:
OCE = Craft Utilization x Craft Performance
The Impact of Improving Both Craft Utilization
and Performance: Improved craft utilization through
more effective planning of all resources will increase available
wrench time. Improved performance results from the fact
that work is planned and the right tools, equipment, and
parts are available made by planning the right craftsperson
or crew for the job with the type of skills needed. Improving
craft performance is a continuous process with a program
for craft skills training and methods improvement to do
the job right the first time in a safe and efficient manner.
The ACE Team Benchmarking Process mentioned earlier provides
reliable planning times based upon “a consensus of
experts” and a tremendous repair methods improvement
effort as benchmark jobs are analyzed.
Example C: What if We Increase Wrench Time
from 30% to 50% and Craft Performance from 80% to 90%?
When we look at the combination of improving both craft
utilization and performance, we see an even greater opportunity
for a return on investment. Let’s now look at a very
realistic 20 point improvement in Craft Utilization and
a 10 point increase in Craft Performance for the same 20-person
craft work force shown back in Table 3 and having an average
hourly rate of $18.00.
• Baseline Cost Per Direct Maintenance Hour @ 30%
Utilization and 80% Performance
20 crafts x 40 hours/week x 52 weeks/year x .30 (CU) x .80
(CP) = 9,984 Direct Craft Hours/Year
= 499 Direct Hours/Craft Position
Baseline Cost: $748,800 ÷ 9,984 Direct Hours = $75
Cost Per Direct Craft Hour
• Improved Cost Per Hour With 50% Craft Utilization
and 90% Craft Performance
20 crafts x 40 hours/week x 52 weeks/year x .50 (CU) x
.90 (CP) = 18,720 Direct Craft Hours/Year
= 936 Direct Hours/Craft Position
Cost Per Direct Craft Hour @ 50% Craft Utilization and 90%
Craft Performance = $40
$748,800 ÷ 18,720 Direct Hours = $ 40 Cost Per Direct
Hour
• Total Direct Craft Hours Gained = 8,736 Total Direct
Hours Gained (87% Increase)
18,720 Hours – 9,984 Hours @ Baseline = 8,736 Direct
Craft Hours Gained
8,736 Hours Gained ÷ 9,984 Hours @ Baseline = .87.5
x 100 = 87% Gain in Direct Craft Hours
• Total Gain in Equivalent Number of Craft Position:
17 Equivalent Craft Positions
20 crafts x .87 (%Hours Gained) = 17.4 Equivalent Craft
Positions
8,736 Hours Gained -:- 499 Hours/Craft Baseline Average
=17.4 Equivalent Craft Positions
• Total Gained Value = $655,200
Gain of 8,736 Direct Craft Hours x $75 Baseline Cost/Direct
Hour =$655,200 Gained Value
$655,200 -:- $748,800 = 87 % Gain from a Baseline of 30%
Wrench Time and 80% Craft Performance
Summary of Our Previous Examples: The
previous examples have illustrated that increasing OCE provides
greater craft capacity and gained value from increased wrench
time. Improving Craft Performance in combination with improving
Craft Utilization simply compounds our return on investment;
an astronomical amount of 87% as shown in Example C.
Examples
Baseline Improve
To: Craft Labor Gain Gained
Value
A CU @40% CU@50% 5 $187,200
B CU@30% CU@50% 13 $497,952
C CU@30% & CP@80% CU@50% & CP@90% 17 $655,200
Where Can We Apply OCE Gained Value: Maintenance
operations that continually fight fires and react to emergency
repairs never have enough time to cover all the work (core
requirements) that needs to be done. Overtime, more crafts
people or more contracted services typically seem to be
the only answers. Improving craft utilization provides additional
craft capacity in terms of total productive craft hours
available.
In relation to OEE, OCE is increased people asset availability
and capacity. It is gained value that can be calculated
and estimated and then measured. The additional equivalent
craft hours can then be used to reduce overtime, devote
to PM/PdM, reduce the current backlog and attack deferred
maintenance which doesn’t go away.
Typically, operations that gain productive craft hours
desperately need to invest the time elsewhere. Likewise,
we can not automatically and indiscriminately reduce head
count when we improve overall craft effectiveness. Indiscriminate
cutting of maintenance is killing the goose that lays the
golden egg.
If an organization is not achieving core requirements for
maintenance the cutting of craft positions to meet budget
is like using blood letting as a new cure for a heart attack.
It just will not work.
Just like the high cost of low bid buying, gambling with
maintenance costs can be fatal. Long-term stabilization
and reduction of head count can occur. Attrition can absorb
valid staff reductions that may result over the long-term.
We also may regain our competitive edge and get back some
of the contract work we lost previously to low performance
and productivity. We cannot indiscriminately cut craft labor
resources when we increase OCE.
Think Profit-Centered: Today’s maintenance
leaders and crafts people must develop the “maintenance-for-profit”
mindset that the competition uses to stay in business. Measuring
and improving Overall Craft Effectiveness and the value
received from improving our craft assets an important part
of total asset management. Profit-centered in-house maintenance
in combination with the wise use of high quality contract
maintenance services will be the key to the final evolution
that occurs.
There will be revolution within organizations that do not
fully recognize maintenance as a core business requirement
and establish the necessary core competencies for the maintenance.
The bill will come due for those operations that have subscribed
to the “pay me later syndrome” for deferred
maintenance. It will be revolution within those operations
that have gambled with maintenance and have lost with no
time left before profit-centered contract maintenance provides
the best financial option for a real solution.
Maintenance is Forever: Contract maintenance will be an
even greater option and business opportunity in the future.
Again we must remember - Maintenance is Forever! Some organizations
today have neglected maintaining core competencies in maintenance
to the point that they have lost complete control.
The core requirement for maintenance still remains but
the core competency is missing. In some cases, the best
and often only solution may be value-added outsourcing.
Maintenance is a core requirement for profitable survival
and total operations success. If the internal core competency
for maintenance is not present it must be regained. Neglect
of the past must be overcome.
It will be overcome with a growing number of profit-centered
maintenance providers that clearly understand Overall Craft
Effectiveness and providing value added maintenance service
at a profit.
References
Dunn, Richard L. (1997), “Plant/Facilities Engineering-Definitions
and Descriptions of Functions and Responsibilities”,
AFE Facilities Engineering Journal, Dec 1997.
Higgins, L.R. Maintenance Engineering Handbook, 5th Edition,
McGraw-Hill, 1995.
Peters, R.W. (1978), “The ACE Team Benchmarking System”,
NC Department of Transportation, Raleigh, NC
Peters, R.W. (1987), The Scoreboard for Excellence, Ralph
W. Peters and PEOPLE, Raleigh, NC.
Peters, R.W. (1994), Achieving Real Maintenance Return
on Investment, Tompkins Associates, Raleigh, NC.
Peters, R.W. (1994), The Scoreboard for Maintenance Excellence,
Tompkins Associates, Raleigh, NC.
Peters, R.W., (1996), Planning for Maintenance Excellence,
Tompkins Associates, Raleigh, NC
Peters, R.W. (1998), “Benchmarking Your CMMS System”,
Industrial Maintenance and Plant Operations, May 1998
Peters, R.W. (1999), The Guide to Computerized Maintenance
Management Systems, Alexander Communications/Scientific
American, New York
Peters, R.W. (2001), Chapter 12- Maintenance in book by:
Tompkins, Jim. Future Capable Company. Raleigh, Tompkins
Press, 2001.
Salvendy, Garviel, Industrial Engineering Handbook, 3rd
Edition, Chapter 59- Maintenance Management and Control
by Peters, R. W., John Wiley and Sons, 2001
Peters, R. W., Maximizing Maintenance Operations for Profit
Optimization, EBOOKAMATIC, Schneiderman and Associates,
LLC, Tulsa, 2002
For a complete electronic copy of this two part presentation
contact:
The Maintenance Excellence Institute
6809 Foxfire Place, Suite 100, Raleigh, NC 27615 Office:
919-270-1173
E-Mail: RalphPetePeters@PRIDE-in-Maintenance.com
WEB SITE: http://www.PRIDE-in-Maintenance.com
Bio of Ralph W. “Pete” Peters
Pete Peters, founder of The Maintenance Excellence Institute
and President of Ralph W. Peters and PEOPLE Inc has over
30 years of practical engineering expertise, operations
management and maintenance responsibilities in both the
public and private sectors. He has helped operations such
as the University of NC-Chapel Hill, Boeing, Heinz, General
Foods, Consolidated Stores, Marathon Ashland Oil, Polaroid,
Great River Energy, Wyeth-Ayerst, Cooper Industries, National
Gypsum, Lucent and Carolinas Medical Center achieve success
in plant, fleet and facilities maintenance operations. Pete
is a senior member of the Institute of Industrial Engineers,
the Association of Facility Engineers and the Society of
Maintenance and Reliability Professionals.
He has served two manufacturing operations as a Plant Manager
and as Director of Facilities Management where he managed
a 225-employee physical plant operation with over $30 million
annual budget and eight million square feet of facilities
including the State Capitol of North Carolina. Responsible
for all physical plant operations, construction renovation,
planning and inventory management. Responsible for commissioning
three major office buildings and a new central steam plant
without significant staff additions.
Also served as Director, Productivity Management, NC Department
of Transportation and helped establish the first fleet maintenance
management system in US for measuring, planning and scheduling
of fleet maintenance work with operator-based preventive
maintenance, planner selection and training, maintenance
performance reporting and team-based maintenance improvement.
During his NC Army National career, directed maintenance
operations at company, battalion and brigade levels to include
command of a direct support maintenance and supply company
in combat zone (Vietnam). Certified as a Total Quality Management
facilitator for the National Guard Bureau.
He is also retired from the US Army Corps of Engineers/NC
Army National Guard (1995) with 28 years of concurrent service
and serving in Viet Nam and during Desert Storm. Pete is
author for the upcoming books; Profit-Centered Maintenance
and PRIDE in Maintenance: I, II and III and was editor/primary
author for The Guide to Computerized Maintenance Management
Systems, Scientific American Newsletters LLC, author of
the maintenance chapters in The Warehouse Management Handbook
and The Future Capable Company from Tompkins Press and John
Wiley’s new 2001 Handbook of Industrial Engineering,
3rd Edition.
A recognized leader in the areas of implementing maintenance
best practices, profit-centered maintenance strategies,
performance measurement, and providing value-added total
operations consulting. He is also the author of over 200
articles and publications and as a frequent speaker has
delivered presentations on manufacturing and maintenance-related
topics worldwide.
Pete received his BSIE and MIE from North Carolina State
University and is a graduate of the US Army Command and
General Staff Course and the Engineer Officers Advanced
Course.
The Maintenance Excellence Institute
Division of Ralph W. Peters and PEOPLE Inc.
6809 Foxfire Place, Suite 100
Raleigh, North Carolina 27615
919-270-1173
www.Pride-in-Maintenance.com |