The most demanding call on
maintenance resources comes when a plant or facility is shut down for an
extended period of time for scheduled maintenance. Usually a large complement of
work must be scheduled into a relatively short period of time. Work schedules
may have to be modified. Special equipment may have to be rented. Contractors
may have to be hired to fill additional labor requirements and special needs.
The scheduled down period is called different names by different industries.
Whether it's called a shutdown, shut-in, down-turn, turnaround, or outage, it
can be the time when the maintenance department shines, or reveals its
functional failings. This is the reason some maintenance managers dread these
down periods. All eyes are focused on the work they do.
Scheduled shutdowns, however, can provide unique opportunities to a
maintenance department not normally available during standard operation or even
during short shutdown periods. Lost capacity can be restored to an overtaxed
facility during an extended shutdown. Major equipment overhauls can be performed
to help prevent future unscheduled shutdowns. Government mandated inspections
and repairs can be accomplished during a shutdown, bringing a plant into better
compliance.
Critical Path Method
Although historically applied to engineering and construction work, the
process of project management is easily adaptable to a maintenance shutdown. One
tool used extensively in project management is the critical path method (CPM).
CPM was developed in the 1950s by U.S. government contractors to speed the
construction of the first nuclear powered submarine, the Nautilus. Over 3,000
contractor and subcontractor companies had to be coordinated to develop the
submarine. Traditionally, a Gantt chart (or bar chart, as it was commonly
called) was used to lay out the tasks to be performed on a timeline. Each bar
represented a task and its length represented the elapsed time required to
complete the task. Gantt charts failed to meet the needs of very large projects
because they did not clearly show the interdependency between different tasks.
The critical path method takes the interdependency of jobs into account. In a
common shutdown, some jobs must follow other jobs, some jobs must precede other
jobs, and some jobs can be performed concurrently with other jobs. Although it
may at first seem difficult to determine all these relationships for each job in
a shutdown, the task can be greatly simplified by asking one question of each
job. That question is, "Which activity or activities must immediately
precede this activity" The result of this exercise will reveal the true
relationship of all jobs in the shutdown.
Assume you have the following list of jobs:
| Activity |
Duration |
Precedent |
| A |
Shut
down and cool down boiler |
24
hrs |
- |
| B |
Inspect
refractory |
4
hrs |
C |
| C |
Open
manways and clean boiler |
4
hrs |
A |
| D |
Replace
bad tubes |
8
hrs |
C |
| E |
Perform
hydrostatic test on boiler tubes |
6
hrs |
D |
| F |
Repair
damaged refractory |
16
hrs |
B |
| G |
Close
manways |
1
Hr |
E,
F |
| H |
Fire
up boiler |
1
hr |
G |
The precedent question was asked of all the activities in the list to
identify the corresponding precedent activities. This questioning process is
referred to as determining the precedent logic. These activities can be tied
together graphically as shown in this diagram.
The resultant diagram is called a logic network or a PERT (Project Evaluation
and Review Technique) diagram. This diagram not only shows the relationship
activities have with preceding activities, but also the succeeding and
concurrent activities. It should be noted that this was all accomplished by
determining the precedent logic only.
The critical path (or sometimes paths) is the one which defines the shortest
period of time in which the project can be completed. As such, it is the series
of interrelated jobs which add up to the longest period time. All other
concurrent paths usually have float or slack time.
Refer back to logic network example. The path which adds up to the longest
total duration consists of activities A, C, D, E, G and H, for a total of 63
hours. This is also the shortest period of time in which the total project can
be completed.
Knowing the critical path is helpful, but knowing the jobs with float or
slack is equally helpful. Activities B and F are non-critical jobs totaling 8
hours. Activities D and E are critical jobs totaling 28 hours and can be
performed concurrently with B and F. The difference in duration between these
two paths is 20 hours. This is called the float or slack. Either B or F can be
delayed 20 hours, or both jobs can be delayed any combination which totals 20
hours without extending the project.
Assume the same crew will have to be used to perform activity D and activity
F. They obviously cannot be performed at the same time with this limitation on
resources. The diagram and float calculation show that activity F can start 24
hours after the start of activity D is begun (4 hour duration of activity B plus
20 hours of float) without extending the duration of the shutdown.
It is important to make the distinction between what facility personnel may
consider to be critical jobs and jobs which fall on the critical path. In
reality they may not be the same. Its all a matter of definition. The job plant
personnel feel is important during the shutdown may require the most resources
or may be the most technically challenging. This job may can be a not be on the
critical path. The critical path method works under the assumption that the
project must be completed in the shortest period of time. If a critical path job
is ignored and allowed to extend beyond its scheduled duration, the duration of
the total project will be extended. This may be more devastating to the
operation of the plant than the extension of a non-critical, albeit technically
challenging.
Project Management Software
The project status should be updated continuously during the execution phase
of a shutdown. This means redrawing the logic network and resulting Gantt charts
to show delays and extended job durations as they occur. A new critical path may
develop so formally non-critical jobs can become critical.
Building and updating a large project manually can be a daunting task that
few would consider practicable. CPM computer programs were developed to solve
these problems in the early 1950s however, these programs were only developed on
mainframe computers for a select few organizations. Project management software
for the PC, developed and improved over the last 10 years, has made project
management more accessible. These programs can help the user organize
interdependent tasks using precedent logic. Resources with different working
hours, schedules and costs can be assigned to these tasks and the results can be
viewed on screen or printed. These software tools are also helpful in analyzing
and communicating project activity. The progress of the shutdown can be tracked
and updated using these programs and the associated costs can be monitored.
Choosing the Right Program
Complex and sophisticated programs are, and have been, available for years.
However, the simpler the program, the quicker someone can start receiving the
benefit.
It's a good idea to try a few programs out to see which one is best for you.
Low end programs are inexpensive, usually under $600 US., while high end
programs can range from $4000 to $12,000 US. Low end programs are sufficient if
you are looking to get a fast start with computerized project management
software. Intelligent, on-line, support is available in some programs. This
feature can lead a novice through the process of project management without much
difficulty.
Most project management programs are designed for general business
applications and not maintenance. However, many offer the ability to customize
the program to your specific needs. Customized fields can be added for entry of
work order numbers or equipment numbers. These fields can be sorted, filtered,
or searched quickly if the need arises. Most can import a simple ASCII or
spreadsheet file. If a computerized maintenance management system (CMMS) can
export to these formats (and most can), then the need for double entry is
eliminated.
Much of the work of a shutdown coordinator requires communicating with other
people about a shutdown in progress. Project management programs can make this
task easy too. Logic network diagrams and Gantt charts can be printed on demand.
Although almost any printer can be used, this is best accomplished using a color
printer or plotter as the output device. Tasks in the critical path can be
displayed in a different color than the other tasks on a logic diagram. These
charts can be annotated by the user to highlight certain sections.
Reports can be customized to present project information the way the user
wants it to be presented. Common canned reports available are
baseline-to-actual, resource allocation, cost distribution, earned value
analysis, and actual to budget. Most users feel a need to modify the output of
these reports in a word processing program.
File import and export capability is built into most of the programs. Not
only can reports be sent to a word processing file, data can be transferred
between different formats. Many of the common formats such as ASCII comma
separated text (.CSV), dBase (.DBF), Lotus 1-2-3 (.WK?), or Excel (.XLS), are
available. It also possible to just cut and paste data between spreadsheets and
softwar programs. Additionally, Microsoft Project can be transferred between
many programs through a format called MS Project Exchange (.MPX) format.
All popular programs operate in a LAN or a client server environment, so
project information can be updated by more than one user. Some programs allow
the user to send project via e-mail to inform project members and update the
project data files. The process is called "distributed or workgroup project
management".
Not only can multiple resources and levels of resource be identified, but
each resource can have its own individual calendar. These calendars indicate the
working days and hours for each resource or resource group. The duration of a
project can be extended if insufficient resources are available. Some programs
have difficulty dealing with shift schedules for resources. If this is a major
requirement, consider some of the high-end programs.
Multiple projects can be worked and managed simultaneously using most project
software. Multiple projects can use the same people or other resources with
overlapping assignments. Handling more than one project with a single project
software file helps to sort out these situations. Some programs feature the
ability to draw resources from a common pool for all projects and improves the
ability to level resources between these projects.
Getting the Most from Project
Software
Some people's initial forays into using project programs were tainted by the
limitations of early software programs, such as the inability
to handle part of an hour or restrictions on the number of resources
which could be defined. Unfortunately, sometimes it was the limited
knowledge of project management methods by the user that led to
the initial frustration with the programs. Many of the software
limitations cited in the early days have been eliminated. The
following rules should be followed to get the most out of project
programs.
Identify jobs by duration. Maintenance planners ordinarily identify job
labor requirements in terms of total labor hours and the craft required to
complete the job. Project management programs require that labor requirements
be identified as elapsed time, resource type, and quantity of the resource.
This distinction allows the software to determine the optimum resource level
required to perform concurrent jobs on the critical and non-critical paths. A
process called resource leveling is employed to delay the start time of
non-critical jobs within float or slack to limit the peak requirements.
Expand your idea of resources. Most people think of a resource as
the technical labor required, such as mechanics and electricians. Inspectors,
safety personnel, engineers, and operations personnel should also be included
as a resource on jobs. Nonhuman resources in short supply, such as cranes,
tools, and laser alignment instruments, should be considered as well. The
process of load leveling will reveal any conflicts with these resources so the
shutdown coordinator can deal with them ahead of time.
Include operations activities. Maintenance people usually only think
of the work that the maintenance department has to do during a shutdown. Often
operations is involved in the preliminary stages to shut down, cool down,
decontaminate, and lock out equipment. All these activities take time during
the shutdown, so get estimates from operations and add these tasks to the
project.
Break larger jobs into smaller segments to separate out the resources
required. For example, an eight hour job may require a mechanic and an
operations person. The mechanic will be involved in the entire job, from start
to finish. The operations person will only be involved in the initial shutdown
of equipment, lock outs, issuing safety permits, and startup. These activities
may only take the first half hour and last half hour of the shutdown. When
using some project programs it is important to break this job into segments so
it is clear the operations person is not required for the entire duration of
the job. This distinction comes in handy during the load leveling process.
Don't assign start times and/or end times when initially entering
project data. Let the project program determine the logical start time
from the precedent logic. Only make a change it if the resultant start time
does not correspond to a convenient time for your shutdown.
Don't limit the number of resources when you initially enter data into a
project management program. The critical path method provides optimal
results when an assumption is made that resources are unlimited. Let load
leveling determine which jobs can be delayed to optimize the use of resources.
The needed delay may be accomplished within the float or slack time available
and not effect the project duration. If some resources are not lowered to the
available level, the duration of the shutdown may have to be extended as a
last resort.
Project management methods can be applied to extended maintenance shutdowns. A
shutdown coordinator can gain even more control over the effort with the use of
new off the shelf software. A professional project management approach will
bring out the best in the maintenance effort. It will also give everyone
confidence that the maintenance department can get the plant running again - on
time and in better condition.