TPM
Implementation Experiences
By: Siam
Yoke ChoyDS Abstract
This paper provides some information on the historical
background of TPM introduction to Infineon Technologies
followed by the chronicle events and experiences learnt
in adopting and adapting TPM development activities to
improve productivity in DS Business Unit. It also identifies
some of the difficulties faced while implementing TPM and
finally proposes some solutions for eliminating them.
Introduction
Like many organizations continue
searching for excellence approaches / programs to improve
their competitiveness, top management introduced Total
Productive Maintenance (TPM) in 1994 to Siemens Malacca
(former company name of Infineon Technologies). At that
time, some selected people were trained on the TPM methodology
however the initiative did not achieve the expected result.
Without giving up the hope, top management made the second
attempt and reinitiated the TPM program in 1996 with the
following main events.
TPM blast-off for management
TPM training for implementation teams
Establish TPM management team
Prepare TPM implementation
plan
TPM training for supervisors & engineers
Pilot TPM teams in Business
Units
TPM training for operators & technicians
2. TPM Development Activities in DS
In mid of 1996,SOT23 is the highest volume runner
in DS and the bottleneck process was at testing area.
Unanimously, DS management has chosen SOT23 inliner as
the pilot project to launch TPM initiative because it
accounted for about 60% of the SOT23 capacity.
Prior to that, the DS management established an
organization structure to coordinate and support the
TPM efforts and activities. This is done through the
formation of the DS TPM Steering Committee team and the
assignment of a full time departmental coordinator to
develop the TPM master plan, control the standardization
of the TPM implementation and regularly review the progress.
In addition, there is a pool of TPM facilitators in DS
Business Unit to implement the TPM development activities.
In the initial roll out of TPM activities, DS
implemented two out of the five fundamental development
activities (pillars) at that time namely Jishu Hozen
Autonomous Maintenance and Kobetsu Kaizen.
Jishu Hozen Autonomous Maintenance (JHAM) ? Teams
of operators performance routine maintenance tasks and
participate in improvement activities that halt accelerated
deterioration, control contamination and maintain optimal
machine conditions. It is typically implemented in eight
steps in our factory
Kobetsu Kaizen (KK, Focused equipment improvement)-
Cross functional project teams composed of people from
production, maintenance, engineering and operators in
activities to minimize equipment losses.
At that point of time, the company was also launching
a new work-floor management system called Self- Managing
Team (SMT) and this had created some confusion in the
early stages as well as priority / focus of both initiatives.
As a result the TPM implementation has taken a longer
time than it should be.
The JHAM implementation is the toughest among
all the TPM development activities as it affect more
people who have to change the ways they do things (culture).
The JHAM journey started off with the 1 st step: initial
cleaning which took about a year to pass the certification.
Step by step, Self-Managing Team implemented the JHAM
from step 1 to step 4 till to-date. Some of the important
requisites for the successful JHAM implementation are
training, step audits, activity board, meeting, One Point
Lesson, and last but not least reward and recognition
system. Furthermore, the assigning of office hour TPM
coordinators by production have greatly helped to facilitate
the JHAM implementation.
Milestone Events
1996 pilot group SOT23 inliner
1997 JHAM Step 1
1998 JHAM step 2
1999 JHAM step 3
2000 JHAM step 4
2001 Skill level 1
?
As for the Kobetsu Kaizen, the formation of the
focused equipment improvement team and ownership by production
has overcome many difficulties faced in most improvement
projects. A full time supervisor who has been empowered
by the superior coordinated the improvement activities
through data collection, equipment loss analysis, countermeasure
implementation and confirmation. In the beginning, that
team mainly focused on reducing equipment losses followed
by expanding the scope to improve operating efficiency
namely change lot time optimization. One of the good
practices was that the team met regularly to discuss/review
the status of the improvement activities so that every
member was informed about their contributions. It is
observed that the team is possible to achieve the dramatic
and sustainable result due to a common shared goal and
good teamwork among the members. In addition, the readily
available and easily accessible equipment performance
measurements namely output, uptime/downtime, overall
equipment efficiency, etc through real time on line monitoring
system (mTPM) has also enabled the change process.
In between, the operators and production technicians
are regularly trained on equipment/process-related knowledge
and skills using a unique and strategic training concept:
One Point Lesson used extensively in the progress of
TPM implementation. Gradually, more and more operators
and production technicians follow established/standard
operating procedures that has one way or the other minimized
the variability in the production process.
Initially, the maintenance department personnel
also participated in the TPM activities through restoring
the equipment to its original and basic conditions as
much as possible. The effect of the restoration if done
objectively will minimize the frequent reactive maintenance
practices. There after, the maintenance personnel will
have more time to involve in higher value-added activities
by continuous improvement of equipment reliability and
maintainability.
In view of the successful result achieved through
this pilot TPM, DS management unanimously decided to
deploy this approach to all product groups. This is made
possible through the assigning of experienced TPM practitioners
from the pilot groups to facilitate the TPM implementation
to all products groups in DS. The leverage of TPM best
practices internally has significantly shorted the learning
cure to achieve similar results in the DS Business Unit.
3. Results
All these TPM development activities which are synergy
to each other have brought about enormous and sustainable
productivity improvement in this pilot project. Before
TPM, the plan module capacity of SOT23 inliner was 80'0
million per year and in most cases the actual capacity
was hugging below this value. Currently, the module capacity
of SOT23 inliner can reach more then 100'0 million. As
a result, the bottleneck has shifted to End Of Line process.
Same approach is replicated to improve the equipment capacity
in others bottleneck processes within all the product groups
in DS.
Summary of some of the results
Capacity of SOT23-2up > 37%
Capacity of SOT3x3-2up > 27%
Capacity of SOD323 > 30%
Capacity of SOT223 > 19% (within 3-4
months)
Leassons Learned
Measuring TPM Effectiveness
For any improvement strategy to be successful
there must be a way to measure how are we doing and how
do we compare with others. TPM uses a key performance
indicator call Overall Equipment Efficiency (OEE) to
measure the productivity (effectiveness and efficiency)
of equipment.
OEE = Availability x Uptime Utilisation x Process
Performance x Quality Yield
Availability is the time the equipment is available
to run (uptime)
Uptime Utilisation is the idling / engineering
time
Process Performance is the actual vs. the design
speed
Quality yield is the total product produced minus
the rejects divided by the total product produced
All these figures are usually expressed in percentage
and higher OEE translates into higher capacity from the
equipment. Surprisingly, the OEE of most equipment range
from 40%-60% when first time take the measurement whereas
the benchmark is 85%. As such, OEE has become the accepted
indicator to assess how plants actually manage their
most expensive asset, the equipment to produce saleable
good with minimum losses and wastes.
Implementing TPM
Although JIPM has established and simplified a
12 steps in TPM development programs (attachment 1),
however most organisations implementing TPM on their
own have never get off the ground the first time and
for those who manage to kick start do not achieve the
expected and sustainable productivity improvement.
Introducing and implementing TPM is not
like a standard project, which normally has a starting,
and an end that seldom exceeds one year. Rather, TPM is
a long range ? living program ? which can take more than
few years to implement and enjoy the lasting benefits
when the whole organisation has become strategy focused
instead of evaluating one new program after another before
implementing TPM thoroughly.
Why is TPM difficult to implement?
In actual fact, implementing TPM is a dramatic
organisational change that can affect organisation structure,
work-floor management system, employee responsibilities,
performance measurement, incentive systems, skill development
and the use of information technology. No wonder the
success rate of such large-scale change is less than
30% for most organisations.
Difficulties faced in TPM implementation
Typically people show strong resistance
to change.
Many people treat it just another ? program
of the month ? without paying any focus and also doubt
about the effectiveness.
Not sufficient resources ( people,money,time,etc.)
and assistance provided
Insufficient understanding of the
methodology and philosophy by middle management
TPM is not a ? quick fix ? approach,
it involve cultural change to the ways we do things
Departmental barrier existing within
Business Unit
Many people considered TPM activities
as additional work/threat
5. Conclusion & Recommendations
TPM is one of the world class lean manufacturing
strategies that is well structured with eight fundamental
development activities and data based approach (OEE)
to improve both the effectiveness and efficiency of any
production system/process involving everyone.
Apparently, successful TPM implementation can
achieve better and lasting result as compared to other
isolated program because there is an ultimate change
in people (knowledge, skills, and behaviour) during the
progress. However don't underestimate the tremendous
efforts required to make that change happened and last.
If we have to start over again?some serious thoughts
Top management (strong & consistent
involvement/commitment)
Create a communication campaign & frequently
reinforce the need to change
Establish the organisation
e.g. steering team/TPM co-ordinator/TPM office
Create a TPM deployment through
sponsor,owner,users and coach
Provide the needed means and
resources (equipment, space, training, money, etc.)
Engage a knowledgeable consultant
Establish reward and recognition
system
Review the implementation
status regularly
Middle management (strong understanding
TPM methodology & philosophy)
Ownership of TPM implementation
( KK & JHAM )
Active promotion and sustenance
(training, coaching, etc.) to the direct staff
Visit the line frequently
to show your interest
Provide supporting environment
by removing barriers
Promote TPM activities through
activity boards and best practices sharing
Direct staff (active participation in TPM activities)
Learn autonomous maintenance
by doing
Suggest new ideas for improvement
Raise equipment/process-related
knowledge and skills
Participate in equipment and
process improvement activities
Teamwork between production,maintenance,and engineering
Use of cross functional teams
is important for TPM success
Information Technology
- Use information technology to gather
equipment information
6. Attachments
Attachment 1: JIPM 12 steps development program
7. Acknowledgements
The author wishes to thank all TPM teams, TPM
Facilitators, and SMT members in DS for their cooperation
and contributions to make TPM successful
8. References
S. Nakajima [1989] ? TPM
Development Program ?, Productivity Press
K. Shirose [1996]? TPM New Implementation
Program in Fabrication & Assembly Industries ?, JIPM
JIPM, Japan Institute
of Plant Maintenance
yoke-choy.siam@infineon.com
|